• Skip to main content
  • Skip to footer
Contact | Show Search
S.B. Ballard Construction Company

Construction Company

Show Search
Hide Search
  • Why Us
    • Company Profile
    • Technology
    • Sustainability
    • Testimonials
    • Affiliations
  • Our Expertise
    • Design-Build
    • Public | Private Partnerships
    • Virtual Design Construction
    • Sustainable Construction
    • Preconstruction
    • General Contracting
    • Construction Management
      (CM AT RISK)
    • Pre-Engineered Metal Buildings – NUCOR Partner
  • Portfolio
    • Commercial
    • Department of Defense
    • Education K-12
    • Healthcare
    • Higher Education
    • Industrial
    • Mixed-Use | Housing
    • Municipal & Government
    • Parking Structures
    • Sports & Entertainment
    • Project Map
  • Live Camera Feeds
  • About
    • Our History
    • Our Leadership
    • Our Culture
    • Diversity Is Power
  • Careers
  • News
  • Contact
  • Bid With Us
    • Bid Portal (SmartBid)
    • Project Portal (SharePoint)
    • Current Bids

VSU Student Housing Designed, Permitted and Constructed in 13 Months

Posted September 14, 2026

When Virginia State University needed student housing on an accelerated schedule, S.B. Ballard delivered Magnolia Hall, a 110,000-square-foot residence hall featuring 125 units and 423 beds. Through a collaborative Design-Build approach, the facility was designed, permitted, and constructed in just 13 months from contract award to occupancy.

Watch the project time lapse video

VSU interior bedroom
VSU lounge area
VSU study area

Site Challenges & Construction Solutions

Site Challenges

S.B. Ballard Solutions

Challenge

Active Campus Environment – Magnolia Hall was constructed adjacent to occupied student housing trailers, requiring safe pedestrian access and minimal disruption to student life throughout construction.

Our Solution

Comprehensive Logistics Planning – Developed a detailed site logistics plan that maintained campus operations,
protected students, and ensured safe access throughout all phases of construction.

Challenge

Limited Site Space – The constrained footprint left little room for jobsite trailers, material storage, deliveries, crane operations, and construction access, requiring careful coordination of all site activities.

Our Solution

Strategic Site Coordination – Implemented just-in-time deliveries, phased material staging, and coordinated crane and vehicle movements to maximize productivity within the constrained site.

Challenge

Complex Underground Infrastructure – Installation of a large underground stormwater retention vault had to be
coordinated alongside utilities, foundations, and building construction within the same limited work area.

Our Solution

Advanced Sequencing & Early Coordination – Integrated stormwater, utility, foundation, and building activities into a single execution plan, allowing multiple scopes to progress simultaneously while maintaining the aggressive schedule.

Accelerating Delivery Through Collaboration & Innovation

Early Collaboration & Design-Build Delivery

Magnolia Hall’s accelerated schedule was driven by early collaboration between S.B. Ballard, Virginia State University, DEB, Niles Bolton, and key stakeholders. Through the Design-Build delivery method, permitting, sitework, utility coordination, procurement, and structural planning advanced concurrently using phased design and early-release packages. This streamlined approach accelerated decision-making, minimized delays, and enabled delivery of the 125-unit, 423-bed residence hall in just 13 months.

Magnolia Hall showcases the advantages of integrating builders, designers, owners, and regulatory stakeholders into a single team from project inception. By aligning goals early and maintaining continuous communication throughout design and construction, the team was able to proactively resolve challenges, maintain momentum, and successfully deliver a high-quality residence hall on an accelerated schedule.

Accelerated Construction Through Precast Innovation

To meet Virginia State University’s aggressive occupancy deadline, S.B. Ballard utilized precast construction to accelerate the schedule while maintaining quality and durability. A total of 534 precast components, including brick-faced exterior panels, were fabricated off-site while foundations, utilities, and sitework progressed simultaneously. Through detailed planning, coordinated deliveries, and strategic crane operations, the team streamlined installation, reduced field labor, and maintained schedule momentum.

What Our Clients Say About Magnolia Hall

Completed Virginia State University Building: Magnolia Hall

Magnolia Hall stands as a testament to what can be achieved through collaboration, innovation, and disciplined project execution.

Filed Under: News

Related posts

S.B. Ballard and the City of Portsmouth celebrate the midway point of construction of the Landing Hotel next to Rivers Casino.

NewsMay 12, 2026

Aviva Pembroke Senior Living Community Official Opening

NewsJanuary 29, 2025

Excellence in Construction Awards

News, AwardsNovember 6, 2024

Footer

Virginia Beach

2828 Shipps Corner Rd.
Virginia Beach, VA 23453
P (757) 440-5555 F (757) 451-2873

Richmond

104 Shockoe Slip Lower Level, Suite C
Richmond, VA 23219
P (804) 343-3433 F (804) 343-3412

Harrisonburg

250 E. Elizabeth St. Suite 117

Harrisonburg, VA 22802
P (757) 689-6817

Employee Portal

Assets | Privacy Policy | Terms & Conditions
© 2026, S.B. Ballard Construction Company, All Rights Reserved